Monday, May 10, 2021

Oriane 2021 Spring Commissioning




















 4/20 First day -

  • Remove winter cover
  • Screwdriver disappears down port deck drain by bad luck
  • Attempt to retrieve screwdriver- unsuccessful
  • Access port for rear of engine measured
  • Bimini and dodger reinstalled
  • Solar option explored

4/24

  • Access port installed in quarter berth
  • Install re-pitched prop
  • Zincs installed
  • Batteries hooked up
  • Depth Transponder tested and proved inop
  • Attempt to retrieve screwdriver- unsuccessful

5/1-5/2

  • Deck sanded, cleaned and lightened
  • Transponder removed (7 hrs of effort)
  • Washed and waxed hull
  • Solar prelim install and functioning
  • Teak oil deck
  • Attempt to retrieve screwdriver - unsuccessful

5/8-5/9

  • Commission engine
  • Remove deck drain hose (very difficult location) to retrieve lost screwdriver (2 hrs)
  • Replace old hose with new – didn’t make sense to put back 39 year old hose due to difficult location
  • Install new depth transducer
  • Paint bottom
  • Clean and wax cabin top
  • Reinstall barbecue on stern rail
  • Reinstall wifi antenna
  • Final install of solar system

Left to do before launch

  • Bring gear to boat including Pip
  • Clean and reposition speed transducer
  • Begin electrical panel clean up
  • Finish bottom paint under stanchions
  • Clean interior
  • Commission and fill water tanks
  • Commission water heater

Launch scheduled 5/18